Logistic Masterstroke

Hilton Rotterdam Hotel

The renovation of a hotel during ongoing operation is one of the greatest challenges to be mastered. Still, we managed to completely gut and refurbish 254 bathrooms in just 6 months without bothering the guests with the construction works.

Due to the ambitious time line it was essential for the success of the project to permanently reconcile and coordinate our work with the other parties involved in the construction. We were able to achieve just that without having to utilise storage capacities on site. We established an external interim storage in order to ensure material flow at all times. The materials were then supplied from there immediately when needed. This allowed us to decisively contribute to the fact that the hotel was handed over on schedule and that it could be utilised at all times during the period of renovation.